APL Apollo
IIF EPC World Awards
Freight Corridor Corp to award Rs 14,000-cr contracts in FY17

Freight Corridor Corp to award Rs 14,000-cr contracts in FY17

Corporation (DFCC), the Indian Railways' arm implementing the ambitious freight corridor project, will award contracts worth Rs 14,000 crore in the current financial year (2016-17) in a bid to quickly wrap up work and meet the 2019 deadline for commissioning the Rs 82,000-crore project.

"By July 2016, we are going to place orders worth Rs 10,000 crore. The balance - around Rs 4,000 crore worth of contracts - will be placed in the rest of the current financial year itself. After this, work will be progressing in every section of DFCC," said a senior executive.

He added the company has so far placed 76 per cent of the contracts for civil works and 63 per cent of electrical contracts, apart from 48 per cent of the total signalling contracts.

For the construction of the Eastern Dedicated Freight Corridor, contracts worth Rs 4,000 crore were awarded in 2013 followed by another Rs 5,000 crore contracts in 2014. Last year, the placed around five contracts for signalling and telecommunication, electrification and civil construction. Similarly, nine contracts were placed for Western Dedicated Freight Corridor.

The executive said the government-owned firm placed contracts worth Rs 24,000 crore in 2015-16 for various works on the freight corridor. "This is compared to Rs 13,000 crore worth of contracts placed in previous six years (2009-14)," he said. DFCC's capex in FY16 stood at Rs 8,600 crore, compared to Rs 2,800 crore in FY15, a three-fold increase. In 2016-17, the company plans an expenditure of Rs 12,500 crore, including Rs 3,500 crore earmarked for land acquisition and the balance Rs 9,000 crore for contractual payments. The DFCC is constructing the 3,350-km-long freight corridor project, including the 1,800 km of its eastern arm between Ludhiana and Dankuni in West Bengal. The Western DFC will come up between Dadri in Uttar Pradesh to Jawaharlal Nehru Port in Mumbai.

 

ON THE RAILS
  • Rs 14,000 cr DFCC planning to place contracts for civil, signalling and telecom, and electrical works in FY17
  • Rs 10,000 cr Contracts to be placed by July; rest Rs 4,000-crore orders by March 2017
  • Rs 24,000 cr Contracts placed in FY16, against Rs 13,000-crore contracts in the previous six years
  • Rs 12,500 cr Spend by SPV under rail ministry in FY17, including Rs 3,500 crore on land acquisition
  • Rs 82,000 cr Project cost. Having already conducted trial run for the first pilot stretch in Bihar, DFCC confident of meeting the 2019 deadline


The project, when commissioned, would take up more than 70 per cent of freight traffic on to its faster, longer and heavier trains.

The Eastern DFC accounts for around 40 per cent of the total project cost. The Phase I of the project between Khurja and Mughalsarai is being funded through 66 per cent debt from World Bank and the rest as equity from the rail ministry.

The Phase II corridor between Mughalsarai and Sonnagar is being funded entirely through government equity, while the third phase between Sonnagar and Dankuni is to be developed on public-private partnership, or PPP mode.

Source: Business Standard




  • About Us

    EPC World Media Group is a one stop knowledge information hub for Infrastructure, EPC and Construction sector. It strives to promote, propagate and assist the decision and policy makers from government and private organizations along with the technology developers and service providers to enhance and develop their capabilities. EPC World Media facilitates knowledge transfer to grassroots and strengthens their productivity.....

    Read More.....
  • Featured Videos

  • Connect Us