Sadbhav Infrastructure Project in a filing to the exchanges has informed its wholly owned subsidiary Sadbhav Bhavnagar Highway has received Provision Completion Certificate for a road project in Gujarat from NHAI.
The filing further stated “National Highways Authority of India (NHAI) vide its letter dated 24th July, 2020 has issued Provisional Completion Certificate with effect from 28th February, 2020 for 34 kms of the project.”
The Provision Completion Certificate was issued to Sadbhav Bhavnagar Highway for the project 'Four laning of Bhavnagar - Talaja section of NH-8E from km. 7.090 (Design chainage km. 6.945) to km. 53.585 (Design chainage km. 54. 990) (Package - I) in the state of Gujarat to be executed on Hybrid Annuity Mode under NHDP Phase-IV'.